One shift's week, 2027MTWTFS48 hours → 46 hours−2 hThrough 2030462027442028422029402030−2 h every Jan

It is December and the plant manager is putting together the January plan. They open the usual spreadsheet: three lines, the headcount for each shift, six eight-hour days and the output per hour of each station. They multiply, get the volume the customer ordered and send it out.

That plan assumes 48 hours per person per week. Starting January 1, 2027, the law allows 46.

What the decree says

On May 1, 2026, Mexico’s Official Gazette published the amendment to the Federal Labor Law that shortens the workweek. Article 59 now reads: “The maximum duration of the ordinary working day shall be forty hours per week” (our translation).

The 40 hours do not arrive all at once. The second transitory article sets a staircase that applies on January 1 of each year:

Year Maximum workweek Overtime hours per week
2027 46 9
2028 44 10
2029 42 11
2030 40 12

The daily limit does not change: eight hours for a day shift, seven for a night shift and seven and a half for a mixed shift. And the seventh transitory article says the reduction cannot lower wages, salaries or benefits.

What you lose every week

Two hours per person sounds small. It is a little over 4% of a 48-hour week. If a hundred people work at your plant, that is 200 fewer hours every week, the equivalent of more than four people on a 46-hour week.

If nothing else at the plant changes, those hours have to come from somewhere. There are three places they can come from:

  • Overtime. Article 66 says it is paid at double rate up to the weekly cap, with the hours “distributed in up to four hours a day, on a maximum of four days” (our translation). In 2027 that cap is 9 hours; anything beyond it cannot exceed four hours and is paid at triple rate (Article 68). If you use two of the nine to recover the hours you lost, you have seven left for everything else: the rush order, the machine that went down, the person who did not show up.
  • More people. More hiring, more training and more supervision.
  • More output per hour. Recovering the time lost today to stoppages, changeovers and waiting for material.

And it is not a one-time event. The staircase drops two hours every January until 2030: eight hours per person per week in total, a sixth of today’s 48.

How to split the 46 hours is not the system’s call

Six shorter days, five eight-hour days, a different shift rotation: that is not a software decision. Article 58 says the workweek “may be distributed by mutual agreement between employers and workers” (our translation), and Article 69 still requires at least one day of rest for every six days worked. You agree on how to split it with your people and review it with your labor lawyer.

What does fall on your system is knowing how many hours you really have once you agree on it.

What your production plan needs to know

The hours available on each shift, not the usual ones. If each line’s capacity is written as a constant in a spreadsheet, the January plan comes out with 48 hours even though the shift now has 46. And the spreadsheet has to be corrected four times, once every January. Hours per shift need to be a value you change in one place.

How much each hour really produces. If you are going to recover capacity through productivity, you need to know where time is lost today: stoppages, changeovers, waiting. The number you carry in your head will not do; we already explained why a high OEE can hide a line that falls short.

How much overtime each person has worked this week. Before assigning Saturday, the supervisor has to know who already has hours. The cap is per person: in 2027, nine hours at double rate per week, no more than four a day and on no more than four days. Ordinary and overtime hours together cannot exceed twelve a day. If that is counted by hand, it is counted too late.

Where the hours come from. Starting January 1, it is also mandatory to record working hours electronically, with start and end times. If attendance and production records live in systems that do not talk to each other, the plan says one thing and the time clock another. The hours the plan uses have to come from the same record.

What to do in the six weeks left

  • Recalculate each line’s capacity with 46 hours per person and compare it with what you have already sold for the first quarter.
  • Check where the workweek is written in your spreadsheets and systems: production plan, payroll, attendance. Each place is a correction that repeats every January.
  • Measure one week of stoppages and changeovers on the line that worries you most. It is the cheapest way to know how much you can recover without overtime.
  • Ask your labor lawyer how the split you agree on with your people stands under the law.

If capacity at 46 hours is not enough for what you have already sold, it is better to find out in November than in the second week of January.

Where we come in

We build manufacturing execution systems for plants in Juárez and El Paso that record what each line produces on every shift and every hour, with its stoppages and their causes, and that take available hours from the same attendance record. That way the January plan comes out with the hours you actually have, and so does the 2028 one. If you want to know where to start, Chira asks you the questions and gives you in writing what to fix first. And if you would rather talk it through, book a call.

References

Related service

Manufacturing Execution

Your production line connected, monitored and optimized in real time.

See the service

Articles on this service

Monthly report87%Line 3and overtimeevery SaturdayHonest mathAvailability86.0%Performance85.3%Quality95.0%OEE69.7%The shift313 minuseful of 450

Manufacturing Execution

Your OEE looks high and the line falls short

The report says 87% and there is overtime every Saturday. Five ways to inflate OEE without lying, what believing it costs, and how to measure an honest one.

6 min read

One lineone monthNetworked PLCSignals onlyManual entryStop reasonsA closed list,same on every shift10–12Before connecting1Named downtime2What a good part is3The machine talks4Network on the floor5The operator gains6An owner from ops

Manufacturing Execution

What has to be ready before you connect a machine

An MES project rarely fails because of the software. It fails because the plant was not ready, and you can know that before signing anything.